All IU GU Plants

How to Perform Additional Excavation/Energy Isolation?

  1. Login as Permit Requester and Go to Live Section of Permit Dash-board.
  2. Select ‘Additional Excavation/Energy Isolation’ Action from Select Action Drop-down List.
  3. For Performing ‘Additional Excavation/Energy Isolation’ on Non-Included Excavation/Energy Isolation on Permit. user have to Select Excavation/Energy Isolation from Work Activity.
  4. If user Selecting Energy Isolation/Adding Equipment to the already Selected Isolation type then the Permit Issued work flow will follow along with Energy Isolation flow.
  5. While Additional Energy Isolation, only selected Isolation In charge for ‘Additional Energy Isolation’ will Isolate the Permit